TenneT Germany Grid Deal Secured for 400 MW / 1.6 GWh Stadorf Battery Project by Elements Green
Elements Green signs TenneT grid connection deal for its 400 MW / 1.6 GWh Stadorf battery storage plant in Lower Saxony, one of Germany's largest projects.
Grid Connection Agreement
Europe
Power
17 November 2026
2 min read
Research Desk
Elements Green Deutschland GmbH has finalized a grid connection agreement with transmission system operator TenneT Germany covering its large-scale battery storage development in Stadorf, Lower Saxony.
Second Agreement Completes the Contractual Framework
The signing, announced, follows the connection construction agreement concluded in October of the same year. Taken together, the two contracts form the key contractual framework for building and subsequently operating the grid connection for the facility.
The project is designed with a planned output of 400 MW and a storage capacity of 1,600 MWh, giving it a storage duration of four hours. At this scale, Stadorf ranks among the largest battery storage projects in Germany and will be connected directly to the extra-high-voltage grid.
Managing Director Highlights Progress on Complex Infrastructure
Michael Zimmermann, Managing Director of Elements Green Deutschland, called the signing another milestone for the development. "Signing the grid connection agreement marks another milestone for Stadorf.
Together with the connection construction agreement, we now have the key contractual foundations in place for connecting this 400 MW project to the grid. This is significant progress for Elements Green and underlines our ability to successfully advance complex energy infrastructure projects of this scale," Zimmermann said. He also placed the project in the wider context of Germany's energy transition.
"Germany needs not only additional renewable generation capacity but, above all, the high-performance and flexible infrastructure to make the energy transition a technical and economic success. Large-scale battery storage systems such as Stadorf will play a central role in this," he added.
Flexibility Services for the German Power System
Once operational, the facility will store electricity during periods of high generation or low demand and release it back to the grid when required. According to Elements Green, Stadorf will contribute to integrating renewable energy, improving the flexibility of the power system and making efficient use of the existing energy infrastructure.
Position Within a Broader Development Pipeline
Stadorf is one element in Elements Green's extensive German battery storage pipeline. The company is developing several large-scale battery storage projects intended for connection to the extra-high-voltage grid and pursues a long-term strategy as an integrated developer, investor and operator of energy infrastructure.
Focus Shifts to Planning and Construction Preparations
With both grid connection agreements now signed, Elements Green is turning its attention to the next stages of technical and commercial implementation. Upcoming work includes detailed planning of the grid connection infrastructure, preparations for construction, and continued coordination with the project and technology partners involved.
Tagged
Also read
Flower and dces Advance 500 MW / 2,000 MWh Ragow Battery Project in Germany
Low Carbon Commissions 65 MW of Essex Battery Storage in the UK
Sonnedix Commissions 125 MWh Tesla Megapack Storage Plant Co-Located with Solar Farm in Japan
Live from the tracker
The projects behind these stories
Capacity, capex, stage, contractors and verified contacts for every project we track, updated daily.