Energy Storage Africa · 14h ago

Mulilo Closes R-Based Financing on Leeuwpoort Battery Project in South Africa

Mulilo secures financial close for 77 MW/308 MWh Leeuwpoort battery storage plant near Carletonville, Gauteng's first at-scale BESS, with BYD tech and 15-ye

Category

Energy Storage

Region

Africa

Industry

Power

Published

17 November 2026

Length

4 min read

RD

Research Desk

· 4 min read

Mulilo Closes R-Based Financing on Leeuwpoort Battery Project in South Africa

South Africa's first large-scale battery energy storage project to reach financial close in Gauteng has been secured by Mulilo, the Cape-headquartered renewable energy developer, which confirmed that its 77 MW / 308 MWh Leeuwpoort Battery Energy Storage System had achieved commercial and financial close.

The facility, to be built near Carletonville in the Merafong City Local Municipality, is the third Mulilo battery storage project to reach financial close in 2026, following the Mercury and Hartebeesfontein BESS projects.

A Grid Anchor in the Mining Belt

The Leeuwpoort facility will connect to the Midas Main Transmission Substation and, according to Mulilo, will strengthen the resilience and flexibility of the national grid in a strategically important industrial and energy-demand region shaped by extensive mining activity. The 77 MW, 308 MWh utility-scale plant is intended to provide critical storage capacity and ancillary services to the transmission system once operational.

The project was awarded under Bid Window 2 of the Battery Energy Storage Independent Power Producer Procurement Programme (BESIPPPP), the national procurement vehicle through which grid-supporting storage facilities are being added to the South African system.

Once running, Leeuwpoort will operate under a 15-year power purchase agreement with the National Transmission Company South Africa (NTCSA). Mulilo describes the financial close as a significant milestone in the delivery of the country's next generation of grid-supporting energy infrastructure, and frames the Gauteng first as an important step in accelerating South Africa's energy transition and grid modernisation.

Technology and Contracting Partners

The project incorporates the Haohan battery energy storage system supplied by BYD Energy storage. Mulilo, acting as lead sponsor, will provide construction management, asset management, operations and maintenance oversight, and social impact management services across the project lifecycle. The company has also pointed to the structure of the ownership and participation arrangements as evidence of its partnership model.

The Reatile Group serves as the project's strategic empowerment partner, while a local community trust is intended to ensure long-term community participation and shared socio-economic benefits for residents of the surrounding municipality.

Executive Commentary

Jan Fourie, CEO of Mulilo, said the financial close marked another significant milestone in the company's commitment to strengthening South Africa's energy system through utility-scale battery energy storage.

"Projects such as Leeuwpoort play a critical role in enhancing grid stability, unlocking network capacity, and improving energy security," he said. Fourie added that, together with the company's partners and with the support of the South African government, Mulilo was proud to deliver lasting value for the country while creating meaningful economic opportunities for local communities.

Sunette Smith, Chief Commercial Officer of the Reatile Group, said the group was proud to partner on Leeuwpoort, describing it as an important investment in strengthening South Africa's energy security and enabling the transition to a more resilient and sustainable energy system.

How the Close Was Assembled

Reaching financial close was made possible, according to Mulilo, through the support of its shareholders, Copenhagen Infrastructure Partners (CIP) and Norfund, together with collaboration from the Reatile Group, the Department of Electricity and Energy, Eskom, the Independent Power Producers Office, the National Transmission Company of South Africa and the Merafong City Local Municipality.

Debt was provided by a consortium of lenders comprising Absa Bank Limited, Nedbank Limited and Standard Bank of South Africa Limited. Mulilo says the participation of the three banks demonstrates continued confidence in the company's project development and delivery capability. Key advisers to the transaction included Arup, Bastion, Bowmans, Deloitte, ENS, Fasken, Marsh and Pepper Tree Capital.

Portfolio and Pipeline

Mulilo is a South African renewable energy developer and independent power producer with a track record in the development, construction and operation of wind, solar and battery energy storage projects.

The company currently operates approximately 450 MW of renewable energy capacity, has a further 1,853 MW under construction, and has more than 1 GW of projects advancing toward financial close.

With Leeuwpoort's financial close following those of the Mercury and Hartebeesfontein BESS projects earlier this year, the company's battery storage pipeline continues to advance.

Mulilo has stated a medium-term ambition of delivering 5 GW of renewable energy assets and says its current portfolio positions it well to realise that goal. Once operational, Leeuwpoort will form part of South Africa's expanding fleet of grid-supporting battery storage facilities procured through BESIPPPP, contributing storage capacity and ancillary services to the national transmission system from its position in Gauteng's mining heartland.

Tagged

Battery Energy StorageFinancial CloseBESIPPPPSouth Africa Energy Transition

Live from the tracker

The projects behind these stories

Capacity, capex, stage, contractors and verified contacts for every project we track, updated daily.

ZVC - Roswell Battery Energy Storage System 18000 MWh · New Mexico, United States · 18,000 MWh · Planning 29SC - Buttonbush Battery Energy Storage System 16000 MWh · California, United States · 16,000 MWh · Planning RSSS - Rex Solaire Battery Energy Storage System 11200 MWh · California, United States · 11,200 MWh · Planning PSR - Prairie Song Reliability Battery Energy Storage System 1150 MW/9200 MWh · California, United States · 1,150 MW · Planning GRIDCO - Odisha Battery Energy Storage System 500 MW/2500 MWh · Odisha, India · 500 MW · Planning MRADPL - Denman Battery Energy Storage System 2400 MW · Australia · 2,400 MW · Planning DSPS - Discovery Battery Energy Storage System 1000 MW · California, United States · 1,000 MW · Planning TSP - Terra Battery Energy Storage System 4500 MWh · Philippines · 4,500 MWh · Planning OS - Sunstone Battery Energy Storage System 1200 MW/7200 MWh · Oregon, United States · 1,200 MW · Planning ZVC - Roswell Battery Energy Storage System 18000 MWh · New Mexico, United States · 18,000 MWh · Planning 29SC - Buttonbush Battery Energy Storage System 16000 MWh · California, United States · 16,000 MWh · Planning RSSS - Rex Solaire Battery Energy Storage System 11200 MWh · California, United States · 11,200 MWh · Planning PSR - Prairie Song Reliability Battery Energy Storage System 1150 MW/9200 MWh · California, United States · 1,150 MW · Planning GRIDCO - Odisha Battery Energy Storage System 500 MW/2500 MWh · Odisha, India · 500 MW · Planning MRADPL - Denman Battery Energy Storage System 2400 MW · Australia · 2,400 MW · Planning DSPS - Discovery Battery Energy Storage System 1000 MW · California, United States · 1,000 MW · Planning TSP - Terra Battery Energy Storage System 4500 MWh · Philippines · 4,500 MWh · Planning OS - Sunstone Battery Energy Storage System 1200 MW/7200 MWh · Oregon, United States · 1,200 MW · Planning