Delta and Samsung C&T File Environmental Impact Statement for 400 MW Vales Point Battery Project in New South Wales, Australia
Delta and Samsung C&T lodge EIS for a 400 MW, 800 MWh battery storage plant at Vales Point in NSW's Hunter region, repurposing coal site land to support th
Battery Storage Plants
Asia-Pacific
Power
12 November 2026
3 min read
Research Desk
A proposal to build a large-scale battery energy storage system on part of the Vales Point Power Station site in the New South Wales Hunter region has formally entered the state planning system.
Delta, working with project partner Samsung C&T Corporation Australia, this week lodged a State Significant Development Application (SSDA) and a supporting Environmental Impact Statement (EIS) with the NSW planning department.
400 MW, two-hour storage proposed at Hunter coal plant site
The proposed battery would deliver up to 400 megawatts of power and 800 megawatt-hours of storage capacity, which the companies say is enough to power around 250,000 homes for two hours.
The project sits within the Hunter-Central Coast Renewable Energy Zone and is intended to strengthen grid reliability and support renewable energy generation as part of NSW's energy transition.
"By repurposing an established energy site and drawing on existing infrastructure, a skilled workforce and close proximity to Sydney and Newcastle, the project will help strengthen grid reliability and support renewable energy generation as part of the region's evolving role in NSW's energy transition," Delta said in a statement.
The company also addressed the proposal on LinkedIn, saying the project "gives new purpose to part of the Vales Point Power Station site, building on its long history of powering NSW."
Nearly 50 years of coal behind the battery plan
The land earmarked for the battery is not an empty corner of the site. According to the planning documents, the proposed BESS area was once occupied by Vales Point A, a coal plant that has long since been decommissioned and demolished.
The surrounding land uses remain consistent with an industrial character, the documents note, including the still-operating Vales Point B coal plant and the nearby Chain Valley Colliery. Two current mining or exploration licences cover the project area, according to the planning documents.
Delta's submission represents the next step in the company's plans for what comes after coal at the site. Vales Point B, a 1,320 MW facility, had originally been scheduled to close in 2029, but in July 2023 the company announced an extension of its technical life that pushed the closure date out to 2033, depending on market conditions.
The extension came against a difficult financial backdrop. In October 2024, Delta revealed it had been refused bank guarantees and was seeking a crucial rule change or exemption from energy market regulators to allow it to keep the plant operating.
18 months of studies and community consultation
Delta says the SSDA and EIS follow 18 months of extensive technical and environmental studies, along with engagement with local residents, businesses, community groups, and stakeholders.
"Thank you to everyone who has shared their views and feedback throughout this process. Your input, including feedback on the project's concept design, has helped shape the project and inform the EIS," the company said.
Residents and other interested parties will now have a formal chance to weigh in. Delta says the community will have another opportunity to have its say when the NSW Department of Planning places the EIS on public exhibition and invites submissions as part of its assessment process.
The battery proposal now sits with the NSW planning department, where the public exhibition phase will form part of the determination process.